Inter Basin Water Transfer link Project

Sustainable Development Networking Programme Bangladesh

Inter Basin Water Transfer Link Project of India

Home Feedback Contact us

 

Inter Basin Water Transfer link Project

 
Home
Inter Basin Water Transfer link Project
Indian National Perspective Plan
Persons Behind The Project
National Water Policy/Act
Scenario of Water Resources of India
Progress of Work So Far
Trans Boundary River Management
Bangladesh's Perspective

 

Time Table

Milestone dates/Time Table for interlinking of Rivers
 

(i) Notification of the Task Force.
By 16.12.2002


(ii) Preparation of Action Plan-I, giving an outline of the time schedules for the completion of the feasibility studies, detailed project reports, estimated cost, implementation schedule, concrete benefits and advantages of the project, etc.
By 30.04.2003


(iii) Preparation of Action Plan-II, giving alternative options for funding and execution of the project as also the suggested methods for cost recovery.
By 31.07.2003
 

(iv) Meeting with the Chief Ministers to deliberate over the project and to elicit their cooperation.
By May/June, 2003
 

(v) Completion of Feasibility Studies (already in progress).
By 31.12.2005
 

(vi) Completion of Detailed Project Reports. (Preparation of DPRs will start simultaneously since FSs in respect of six river links have already been completed).
By 31.12.2006
 

(vii) Implementation of the Project (10 years).
By 31.12.2016
 

Source:  Ministry of Water Resources, Government of India.

 

Inter Basin Water Transfer link Project

Background
Resolution
Order
Press Release
Address by President of Indian
Speech of the Prime Minister of India
Order of the Supreme Court
Time Table
National Commission
Task Force
TOR of Task Force
Cost of The Project
Details of Proposed Links

 


Home Feedback Contact us